The pinnacle of technology is not cheap:
[...] Micron's latest investment will become the first all-new memory manufacturing fab constructed within the U.S. in the past two decades. According to Micron, only 2 percent of memory available on the global market is produced domestically.
Micron's current timetable states that actual construction on the Boise fab will commence in early 2023. Cleanroom space will become available in phases, starting in 2025. Later that year, Micron will be ramping production of DRAM products. However, the fab won't operate full-tilt until the latter part of this decade, once the entire 600,000 square feet of cleanroom space becomes available.
Micron will spend a mind-boggling $15 billion for just this one location.